Construction Permit For High-Rise From Capital Development Authority, Islamabad
PIDE SLUDGE SERIES NO. 03
QR Code https://file.pide.org.pk/pdfpideresearch/sludge-series-03-obtaining-construction-permit-for-high-rise-from-cda.pdf

Construction Permit For High-Rise From Capital Development Authority, Islamabad

Publication Year : 2021
Explore More : Rasta Sludge Series

It takes almost 3 years to seek approval of the CDA for the construction of a high-rise building. The biggest source of sludge comes from the NOC required from Civil Aviation Authority and the Environmental Protection Agency – the two agencies together take around 1.5 years (9 months each) to allow construction of a high-rise building. (This sludge can be almost eliminated, in the manner described below).